fbpx
Victorian Plumbing Solar PV Installation

Victorian Plumbing Solar PV Installation

Victorian Plumbing Solar PV Installation

In a move that’s expected to reduce its carbon footprint significantly, Victorian Plumbing, a leading UK-based bathroom and kitchen solutions provider, has installed a massive solar PV system at their new site in Leyland. The impressive installation, designed and delivered by Genfit, is set to generate enough clean energy to power the company’s operations for months to come.

The solar PV system, spanning an impressive 823.62kWp of installed DC power, is our largest commercial solar installation of the year so far taking around 3 weeks to complete. Comprising 1554 high-efficiency solar panels from Longi, the system will generate approximately 656.94 megawatt-hours of electricity annually, equivalent to 5,835 trees being planted.

The solar PV system will provide a significant portion of the energy needed to power Victorian Plumbing’s offices, warehousing facilities, and manufacturing operations on site. This will not only reduce the company’s reliance on fossil fuels but also help mitigate its carbon footprint by avoiding an estimated 127 tons of CO2 emissions each year.

Genfit’s team of experts worked closely with Victorian Plumbing to design and install the solar PV system using the Solaredge Designer App, ensuring seamless integration with the existing infrastructure. The company’s state-of-the-art equipment and expertise enabled the team to optimize the system’s performance and maximize energy generation.

Director of Genfit Dave Houson had this to say about the installation “We are extremely happy to have successfully installed a 823.62 kWp solar PV system on our most significant project of the year so far at Victorian Plumbing using the best technology from Solaredge and Longi. This shows our dedication to building a greener future. This installation involved overcoming various challenges, including working within tight timeframes and ensuring the highest safety standards throughout the project. By implementing a safe system of work, we navigated these complexities effectively, ensuring the project was completed without incident.

This achievement is a clear demonstration of our commitment to integrating green energy solutions for businesses. The positive outcome has not only exceeded our client’s expectations but has also set a new standard for sustainability within the industry. The successful installation has reduced the carbon footprint of this major development significantly, contributing directly to a more sustainable future.

Being part of such a large-scale project allows us to showcase our expertise in renewable energy solutions. We’re thrilled to have partnered on a project that will have lasting positive impacts for years to come. For other businesses looking to implement similar solutions, we bring the same dedication, expertise, and commitment to safety, ensuring successful outcomes for projects of all sizes across the country.”

This significant investment in renewable energy underscores Victorian Plumbing’s commitment to sustainability and corporate social responsibility. As businesses continue to prioritise environmental sustainability, Genfit remains at the forefront of delivering customised solar solutions that meet their unique needs and goals.

Installed DC Power (kWp)

Max Achieved AC Power (kW)

Annual Energy Production (MWh)

CO2 Emission Saved (Tonnes)

Equivalent Trees Planted

Installation Video

Getting Our B Corperation Certification

We got our B Corperation certification whilst this project was on going so what better way to show off our B Corperation certification by celebrating it on our biggest commercial install of the year.

We are so proud to have achieved such a high score – but we are not stopping there. Ever since our inception, we have had core values of people and planet before profit and so becoming a Bcorp was a decison that was part of our DNA already. However the structure of the BIA assessment has already made us better and we know how to continue to improve which we are 100% commited to.

We Are B corp Certified

Technology

Solar Panel

Longi Solar, LR5-66HTH-530M x 1554

Warranty

Output Warranty Term: 25 years

Materials Warranty Term: 12 years

Efficiency

22.3%

Dimensions

2094 x 1134 x 35mm

Weight

26 kg

Inverter

SolarEdge 100K Synergy Manager x 5

SolarEdge 90K Synergy Manager x 1

Optimiser

Solaredge S1200 x 380

Make Enquiry

Please fill in your details below and we will be in touch as soon as possible

Agreement

One City Place

One City Place

One City Place

Genfit has successfully delivered a solar photovoltaic (PV) system at One City Place, an iconic office development, furthering the building’s commitment to sustainability and energy efficiency.

This installation exemplifies how modern commercial spaces can effectively integrate renewable energy solutions to reduce operational costs and environmental impact. The system, featuring an installed DC power of 60.42 kWp, a maximum achieved AC power of 50 kW, and an annual energy production of 41.27 MWh, provides reliable, clean energy to meet a significant portion of the building’s energy demands. Using SolarEdge inverters and Longi solar panels, the system benefits from state-of-the-art technology known for its efficiency and durability, ensuring optimal performance and supporting the building’s sustainability objectives. Environmentally, the installation saves 7.98 tonnes of CO₂ emissions annually, equivalent to planting 367 trees, underscoring the role of renewable energy in reducing the carbon footprint of commercial properties. Operationally, the system reduces electricity costs, enhances energy independence, and boosts the property’s sustainability credentials, making it more appealing to tenants and stakeholders committed to green initiatives.

This project is a testament to how commercial buildings can successfully transition to renewable energy, contributing to broader climate change efforts and environmental stewardship, while delivering long-term financial and environmental benefits.

Installed DC Power (kWp)

Max Achieved AC Power (kW)

Annual Energy Production (MWh)

CO2 Emission Saved (Tonnes)

Equivalent Trees Planted

Installation Video

Quote From Our Director

“At Genfit, we are proud to be a part of One City Place’s journey towards sustainability. This installation is a prime example of how commercial properties can harness the power of solar energy to reduce their environmental impact while also realising long-term energy savings. By using cutting-edge technology from SolarEdge and Longi, we’re able to deliver high-performance solutions that not only meet today’s energy needs but also contribute to a cleaner, greener future.”

One City Place Crane Lift

Technology

Solar Panel

Longi Solar, LR5-66HTH-530M x 114

Warranty

Output Warranty Term: 25 years

Materials Warranty Term: 12 years

Efficiency

22.3%

Dimensions

2094 x 1134 x 35mm

Weight

26 kg

Inverter

SolarEdge 25K x 2

Optimiser

Solaredge S1200 x 59

Make Enquiry

Please fill in your details below and we will be in touch as soon as possible

Agreement

Secure Trust Bank Solihull

Secure Trust Bank Solihull

Secure Trust Bank

In Early January we installed a 70.49 kWp solar PV system at Secure Trust Banks Solihull site following our successful installation at one of their other sites based in Cardiff. The system consists of 133 LR5-66HTH-530M Longi Solar Panels with 67 Solaredge S1200 optimisers and 2 Solaredge 25K inverters. 

Our goal is to continue installing solar panels on commercial buildings across the United Kingdom and helping the environment by reducing carbon emissions for businesses. This installation will save around 12 tonnes every calendar year which is the equivalent to 536 trees being planted. Also the 60.40 MWh of solar energy being produced annually from the solar-powered system will help power the electricity day to day across the site and will dramatically drop the company’s expenses in electricity bills.

Installed DC Power (kWp)

Max Achieved AC Power (kW)

Annual Energy Production (MWh)

CO2 Emission Saved (Tonnes)

Equivalent Trees Planted

Installation Video

Technology

Solar Panel

Longi Solar, LR4-72HPH-455M x 758

Warranty

Output Warranty Term: 25 years

Materials Warranty Term: 12 years

Efficiency

20.9%

Dimensions

2094 x 1038 x 35mm

Weight

23.5 kg

Inverter

SolarEdge 100K Synergy Manager x 2

SolarEdge 66.6K Synergy Manager x 1

Optimiser

P950 x 380

Make Enquiry

Please fill in your details below and we will be in touch as soon as possible

Agreement

Beko, Watford Solar PV Installation

Beko, Watford Solar PV Installation

Beko, Watford Solar PV Installation

Introduction

Beko, a leading home appliance brand, has demonstrated its commitment to sustainability and renewable energy by installing a state-of-the-art solar photovoltaic (PV) system at its Watford facility. This case study outlines the project’s objectives, implementation, challenges, and outcomes.

Objectives

The primary objectives of the solar PV installation at Beko’s Watford facility were:

Reduce Carbon Footprint: Lower the company’s reliance on non-renewable energy sources and reduce greenhouse gas emissions.

Cost Savings: Decrease electricity costs through the generation of on-site renewable energy.

Corporate Responsibility: Enhance Beko’s reputation as an environmentally responsible company.

Energy Independence: Increase energy independence and resilience against grid power fluctuations and price increases.

Planning and Design

The planning phase involved a thorough assessment of the facility’s energy needs and the potential for solar energy generation. Key considerations included:

Roof Space: The available roof space was assessed to determine the maximum number of solar panels that could be installed.

Energy Consumption: Historical energy consumption data were analysed to size the system appropriately.

Orientation and Shading: The orientation of the building and potential shading from nearby trees were evaluated to optimise the placement of solar panels.

System Specifications

The solar PV system installed at Beko’s Watford facility includes:

Total Capacity: 88.40 kW

Number of Panels: 208 SOLARWATT panels

Inverters: 1 Solaredge 66.6K Synergy Manager

Mounting System: Tilted mounting frames to maximize solar exposure

Installation

The installation process was completed over a period of two weeks, Key steps included:

Installing Panels: Lifting panels to the roof and installing them

Electrical Integration: Connecting the PV system to the facility’s electrical infrastructure.

Commissioning: Testing and commissioning the system to ensure optimal performance.

 

Conclusion

The solar PV installation at Beko’s Watford facility is a testament to the company’s commitment to sustainability and innovation. By investing in renewable energy, Beko not only enhances its corporate image but also realizes significant cost savings and environmental benefits. This project serves as a model for other companies looking to transition to renewable energy sources.

Future Plans

Building on the success of this project, we plan to work with Beko again on their headquarters in Tamworth which is a bigger project and cant wait to get started.

By continuously striving for sustainability, Beko reinforces its position as a leader in the home appliance industry.

Installed DC Power (kWp)

Max Achieved AC Power (kW)

Annual Energy Production (MWh)

CO2 Emission Saved (Tonnes)

Equivalent Trees Planted

Installation Video

Working With Advantage Utilities

Working with Advantage Utilities on the solar PV installation at Beko’s Watford facility was a seamless and highly productive collaboration. Advantage Utilities brought their extensive expertise in renewable energy solutions, providing comprehensive support from initial feasibility studies to the final commissioning of the system. Their professional team conducted thorough site assessments, meticulously planned the installation process, and ensured compliance with all regulatory requirements. Throughout the project, Advantage Utilities maintained clear communication, addressing any challenges promptly and efficiently. Their commitment to quality and customer satisfaction was evident in every phase, resulting in a solar PV system that not only meets but exceeds Beko’s sustainability goals. This partnership has been instrumental in achieving a successful transition to renewable energy, paving the way for future collaborations.

Technology

Solar Panel

SOLARWATT, Panel vision AM 4.5 pure 425 (Glas-Glas) x 208

Warranty

Product Warranty: 30 years

Performance Warranty: 30 years

Efficiency

21.8%

Dimensions

1,722 x 1,134 x 35mm

Weight

24 kg

Inverter

SolarEdge 66.6K Synergy Manager x 1

Optimiser

Solaredge S1000 x 208

Make Enquiry

Please fill in your details below and we will be in touch as soon as possible

Agreement

Well Fed at Home Solar PV Installation

Well Fed at Home Solar PV Installation

Well-Fed at Home Solar Panel Installation

Back in May we completed a 102.66 kWp solar panel installation at Well-Fed at Home based in Deeside. The solar panel system was designed to harness the power of the sun and reduce the factories carbon footprint. Genfit’s expert team worked closely with Well Fed at Home to ensure a seamless installation process, ensuring minimal disruption to daily operations. With this new solar installation, Well Fed at Home is now able to generate clean energy and reduce its reliance on traditional fossil fuels, aligning with its commitment to sustainability and community well-being. The installation is also expected to save the store thousands of pounds on energy costs over the life of the system.

The 102.66 kWp system consists of 236 Longi solar panels with half the amount of optimisers connecting to 2 solar panels each wired up to the two SolarEdge 33.3K inverters which were placed in the office above the factory. The system is estimated to produce 82.73 MWh of solar energy every year and reduce there carbon footprint by 16 tonnes which is equivalent to 735 trees beign planted.

Installed DC Power (kWp)

Max Achieved AC Power (kW)

Annual Energy Production (MWh)

CO2 Emission Saved (Tonnes)

Equivalent Trees Planted

Technology

Solar Panel

Longi Solar, LR5-54HTH-435M Explorer x 236

Warranty

Output Warranty Term: 25 years

Materials Warranty Term: 12 years

Efficiency

20.9%

Dimensions

2094 x 1038 x 35mm

Weight

23.5 kg

Inverter

SolarEdge 33.3k x 2

Optimiser

SolarEdge S1200 x 120

Make Enquiry

Please fill in your details below and we will be in touch as soon as possible

Agreement